|
Power Delivery | Transmission System | Load Management | Tree Planting and Power Lines (PDF) | OASIS | Interconnection Guidelines and Forms | Best Management Practices | Project Updates Chisago to Apple River ProjectDairyland Power Cooperative, together with Xcel Energy, is working to bolster the electrical system in western Minnesota and northwest Wisconsin by upgrading existing power lines and substations, and constructing some new lines in the area between Chisago County, Minn., and Polk County, Wis. Construction of the transmission line is scheduled from mid-February through the end of 2010. The project encompasses 25 miles of transmission line between St. Croix Falls and Range, Wis. For information on project permitting and need, please see the Wisconsin Public Service Commission website, www.psc.wi.gov, and look up docket numbers: 1515-CE-102 and 4220-CE-155. For a map of the project area, please click on this link.(pdf) For information on project construction, please click on this link. |



